How long does it take to install containment?
Installation time depends on the containment type and site conditions. For standard horizontal or vertical containment, a typical installation can take anywhere from a few hours to one day with a two-person team, usually covering runs of about 6–7 meters. Larger installations generally add roughly one additional day per similar section.
Actual timelines vary based on factors such as design complexity, the number of custom components, and whether retrofitting is required. Modifications to existing infrastructure, for example, creating cable cutouts or working around obstructions, can also increase installation time.